The Yangzhou Cogeneration Plant
 
Unit
Year 2006
Year 2007
Year 2008
Year 2009
Installed Capacity at Year End MW 2 x 24 2 x 24 2 x 24
2 x 24
Average Utilization Hours Hours 7,098 7,702 6,468
6,431
Gross Generation MWh 340,710 369,728 310,459
308,680
Power Sales MWh 304,830 328,540 277,310
274,490
Steam Extraction Capacity tonne/h 160 160 160
160
Total Steam Output tonne 98,243 301,050 206,705
255,411
Steam Sales tonne 61,726 226,874 167,628
199,858